1.0 TITLE: Project Status Reporting
1.1 EFFECTIVE DATE: October 26, 2000
REVISED:
April 24, 2003
1.2 TYPE OF ACTION: Update
3.0 ORGANIZATIONS AFFECTED: All Branches, Boards, Divisions, Departments, and Agencies, of state government, hereafter referred to as entities.
4.0 REFERENCES:
5.1 Cumulative cost means the total expenditures, from all sources, for any information technology project by one or more state entities to meet project objectives from project start to project completion or the date and time the project is terminated if it is not completed.
5.2 Information technology project means a project for a major computer, telecommunications or other information technology improvement with an estimated cumulative cost of $250,000 or more and includes any such project that has proposed expenditures for: (1) new or replacement equipment or software; (2) upgrade improvements to existing equipment and any computer systems, programs or software upgrades therefore; or (3) data or consulting or other professional services for such a project.
5.3 ITEC - Refers to the Information Technology Executive Council, duties defined in K. S. A. 1998 Supp. 75-7202, 75-7203.
5.4 CITO – Refers to the Executive, Legislative or Judicial Branch Chief Information Technology Officer, duties defined in K. S. A. 1998 Supp. 75-7205, 751-7206, 75-7207.
5.5 Project change or overrun means any of the following: (1) Any change in planned expenditures for an information technology project that would result in the total authorized cost of the project being increased above the currently authorized cost of such project by more than either $1,000,000 or 10% of such currently authorized cost of such project, whichever is lower; (2) any change in the scope of an information technology project, as such scope was presented to and reviewed by the joint committee or the chief information technology officer to whom the project was submitted pursuant to KSA 79-7209 and amendments thereto; or (3) any change in the proposed use of any new or replacement information technology equipment or in the use of any existing information technology equipment that has been significantly upgraded.
5.6 Project change request means any agreement between the entity and a contractor that will result in a change to the currently authorized cost of the project.
6.1 The project status reporting procedures defined in this policy supersede the previous project status reporting procedures as defined in Kansas Information Resource Council Policy # 2400. The revised procedures apply to all new projects and all current projects for which the required information is available.
7.1 All project progress reports are due in the office of the Chief Information Technology Officer by the 10th of the month following the end of the reporting period. The Chief Information Technology Officer may require more frequent reporting for high risk projects.
8.1 Heads of entities are responsible for establishing procedures for their organization's compliance with the requirements of this policy.
at http://da.ks.gov/kito/itprojectreporting.htm
at http://da.ks.gov/kito/itprojectreporting.htm
at http://da.ks.gov/kito/itprojectreporting.htm
at http://da.ks.gov/kito/itprojectreporting.htm
Entities will include a copy of any project-change-request that has been approved by the entity during the reporting period if that change request will result in a change to the currently authorized cost of the project. Each project change request should be accompanied by an analysis of impact on the project’s schedule and resources.
at http://da.ks.gov/kito/itprojectreporting.htm